A ROOF!

The H*VMI Office has a roof! The trusses got craned onto the frame all in one day. It was amazing to see the guys working together - some high, some low - quickly moving over 50 individual trusses onto the roof and securing them to the frame and to each other. The next day they began covering the roof to prepare for shingles. Then they built out the dormers you can see on the lower right picture. When I stand in the office now, it really feels like the inside of a building, not just a concrete pad on a pile of dirt! God has been so gracious with the weather and the schedules of the different subcontractors. Please continue to pray for safe and efficient progress. Weather is still a prayer request as the rest of the property continues to be excavated. However, once we have shingles and siding, AMES will be able to work inside without too much worry about the weather outside. PRAISE HIM for all His provisions through this building process.